Design phase
Contents |
[edit] Introduction
In very general terms, design is the realisation of an idea, or the resolution of requirements, through means of communication such as drawings, plans, specifications and models. These can then be used to enable items to be created or issues resolved.
The process for completing the design and construction of a building is often divided into notional ‘stages’ or phases. This can be helpful in establishing milestones for the submission of progress reports, the preparation of information for approval, client gateways, and for making payments. However, there is a great deal of ambiguity between the naming of stages and the definition of what individual stages include. For more information see: Design stages.
In a traditional building contract for a stright-forward building, the design phase might comprise two very broad stages:
[edit] Concept design
Concept design generally takes place after feasibility studies and options appraisals have been carried out and a project brief has been prepared. Whilst these phases may include the preparation of drawings and other studies, they are generally not considered to involve 'desgin'.
The concept design represents the design team's initial response to the project brief, adn articulates the broad outlines of function and form.
Some designers differentiate between 'concept design' and 'scheme design'. In this case, the 'concept' is the initial design idea, whereas the 'scheme' develops the concept, taking on board more functional and practical considerations. Most project plans have now combined these two steps into the single stage 'concept design', or 'concept'.
During the concept design stage, the design team will develop:
- The design concept.
- Outline specifications.
- Schedules of accommodation.
- A planning strategy.
- The cost plan.
- Procurement options.
- Programme and phasing strategy.
- Buildability and construction logistics.
At the end of the stage, the consultant team will typically prepare a concept design report which records the basic design concepts for the preferred option that might be worth further developing in the detailed design stage.
The project brief will generally continue to develop as the concept design is prepared, but is then frozen at the end of the concept design stage. An application for planning permission might be made during the concept design stage. This is likely to be an outline planning application if made at the beginning of the stage or a detailed planning application if made once the concept design is complete.
For a more detailed account see: Concept design.
[edit] Detailed design
Concept design is followed by 'detailed design' or 'developed design' during which all the main components of the building and how they fit together are described.
By the end of the detailed design process, the design should be dimensionally correct and co-ordinated. However, technical aspects of the design may require further development, design by specialists may not yet have been fully incorporated into the design and it will not have been packaged for tender.
Detailed design should provide sufficient information for applications for statutory approvals (such as building regulations approval) to be made.
Items that are typically developed in detailed design include:
- Overall layout.
- Road layouts and landscape.
- Operational flows and departmental operational policies.
- Horizontal and vertical circulation routes, including accessibility requirements.
- Schedules of accommodation, including occupancy numbers for each space.
- Identification of standard and non-standard room layouts.
- Room data sheets, if appropriate.
- Building dimensions and gridlines.
- Architectural plans sections and elevations of buildings, parts of buildings and drawings.
- Outline specification including schedules of components, defining the performance and/or material standards required (including colours).
- Elements of design that require specialist input or early choice of manufacturer. Designers should investigate suppliers certificates, warranties and compliance with standards.
- Requirements for mock-ups, testing, samples or models necessary to satisfy performance or public relations requirements (including computer generated images).
- Key assemblies, component drawings and schedules.
- Structural plans sections, elevations and specifications.
- Building services plans, sections and elevations.
- Defining of phases if the project is to be phased.
- Safety strategy
- Fire strategy
- Acoustic strategy;
- Use of materials and potential for re-use, recycling and waste handling (see site waste management plan).
- Detailed cost plan showing the capital and lifecycle costs for all the components, and
- Risk assessment including operational issues
For more information see: Detailed design.
[edit] Technical design
Increasingly, the complexity of buildings involves a further stage, sometimes referred to as 'technical design'. This includes project activities that take place after the detailed design (or 'developed design' or 'definition') has been completed, but before the construction contract is tendered or construction begins.
By the end of the stage the architectural, structural and mechanical services design and specifications should describe all the main components of the building and how they fit together, any performance specified work should be defined and there should be sufficient information for applications for statutory approval to be completed. Room data sheets are also likely to have been prepared along with outline technical specifications.
For more information see: Technical design.
[edit] Related articles on Designing Buildings Wiki
- Brainstorm.
- BREEAM launches local planning authority guidance.
- Briefing documents.
- Computer-generated imagery (CGI).
- Concept design report.
- Concept architectural design.
- Concept architectural design checklist.
- Concept structural design.
- Concept services design.
- Design and its visual elements.
- Design proposals.
- Detailed design.
- Feasibility studies.
- Mood board.
- Options appraisal.
- Schedule of accommodation.
- What is design?
- Vision.
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.